Master Schedule

Use the Master Schedule function to create a master schedule of the assembled items you need to build with either Bills of Material/Kitting or MFG Production as a planned response to the forecasted demand predicted by an item's Sales Forecast. Consider the master schedule your build schedule in terms of specific item IDs, quantities, and dates.

Keep in mind that sales forecast quantities for kits affect the master schedule for assembled items included in the kit; however, kits themselves do not have master schedules since kits are not stocked but are assembled at point-of-sale.

Use the Extend button on the toolbar to extend the selected schedule. In the Extend Master Schedule dialog box that appears, select a Period Definition ID and Begin Date to use for the schedule extension, then click the OK button to return to the main screen.