Schedules

The Schedule is used to assist in the calculation of how long products will take to complete. Schedules are generally intended to be used with Machine Group resources but could be used to a limited extent with Labor or Work Centers.

The Schedules function defines the daily and hourly availability of a given resource. Within each Schedule there are multiple date ranges or days, and within each date range or day--called Availability Descriptions--there are usually multiple time frames. Each one of these shows availability in terms of a start time and a finish time.

The Schedules function allows you to specify the availability of shifts, the hours in each shift, plant closings, special holidays, planned repairs or maintenance, and so on. You can maintain as many schedules as you like. You can then assign schedule IDs to specific work centers, machine groups, or labor types so that specific availability or capacity can be calculated. To begin, set up one schedule and add others as you need them.